Albemarle County Unincorporated, Virginia · General provision
Sec. 4.2.1
Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Building site composition
Building site cannot include critical slopes, flood hazard overlay, underwater areas, within 200 ft of reservoir flood plain, or stream buffer.
- SetbackSetbackThe distance a building must be held back from a lot line. from reservoir flood plainFloodplainLand expected to flood at a stated frequency, where building carries extra conditions.200 ft
Within 200 horizontal feet of the 100-year flood plain of any public water supply reservoir.
From the ordinance
No lot other than a special lot shall have less than one building site, subject to the following: ... building site may not contain critical slopes, flood hazard overlay, under water, within 200 feet of 100-year flood plain of public water supply reservoir, or within stream buffer.