Albemarle County Unincorporated, Virginia · General provision

Sec. 5.1.65

Extracted standards

6 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Noise

  • Generator exercise hours

    Routine generator exercise maintenance is limited to Monday—Friday between the hours of 10 a.m. and 4 p.m.

  • Generator sound limit70 dBA

    Generators must be enclosed in a level 3 enclosure or other enclosure limiting sound to 70 dBA measured 23 feet from the generator.

Other

  • Closed loop or recycled water cooling

    Any water cooling must use a closed loop or recycled water system.

  • Public water and sewer required

    Data centers must be served by public water and public sewer.

Setback

From the ordinance

Data centers must be served by public water and public sewer. Any water cooling must use a closed loop or recycled water system. Data center buildings and all associated equipment and accessory structures (such as generators, HVAC, and battery backup) must be set back at least (i) 200 feet from all lot lines and (ii) 500 feet from the Rural Areas zoning district. Routine generator exercise maintenance is limited to Monday—Friday between the hours of 10 a.m. and 4 p.m. Generators must be enclosed in a level 3 enclosure or other enclosure limiting sound to 70 dBA measured 23 feet from the generator.
Sec. 5.1.65