Albemarle County Unincorporated, Virginia · General provision
Sec. 5.1.40
Extracted standards
4 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Maximum duration for temporary non-emergency event7 days
The MPWSF may be placed on the site for a maximum of seven consecutive days
- Maximum number of temporary non-emergency events per year2 events
may not be placed on any site for any temporary non-emergency event more than twice in a calendar year
- Zoning clearance within 45 days for state of emergency45 days
the owner must obtain a zoning clearance under section 31.5 within 45 days after placing a MPWSF on any site
- Zoning clearance required
The owner must obtain a zoning clearance under section 31.5 prior to placing a MPWSF on any site for a temporary non-emergency event.
From the ordinance
Mobile personal wireless service facilities are not subject to any requirements of section 5.1.40, and are otherwise permitted by right in any zoning district, subject to the following: ...