Extracted standards
2 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Inspection frequency14 days
at least once in every two-week period
- Post-storm inspection48 hours
within 48 hours following any runoff producing storm event
From the ordinance
Provide for an inspection during or immediately following initial installation of erosion and sediment controls, at least once in every two-week period, within 48 hours following any runoff producing storm event, and at the completion of the project prior to the release of any performance bonds