Abingdon, Virginia · General provision

Section 8-5-14(b)

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Inspection frequency14 days

    at least once in every two-week period

  • Post-storm inspection48 hours

    within 48 hours following any runoff producing storm event

From the ordinance

Provide for an inspection during or immediately following initial installation of erosion and sediment controls, at least once in every two-week period, within 48 hours following any runoff producing storm event, and at the completion of the project prior to the release of any performance bonds
Section 8-5-14(b)