- Additional restoration time under federal disaster declaration2 years
an additional two years is permitted to complete the restoration
- Damage threshold for restoring to original nonconformingNonconformingLawful when built, but not compliant with the rules now in force; usually allowed to continue but not to expand. condition50 pct
If such building or structure is damaged greater than 50% and cannot be repaired, rebuilt or replaced except to restore it to its original nonconforming condition, the owner shall have the right to do so.
- Restoration completion period2 years
completed within two years of the date of the casualty
From the ordinance
may repair, rebuild, or replace without the need to obtain a variance, provided such restoration ... is completed within two years of the date of the casualty.