Extracted standards
6 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Floodplain
- Lowest floor elevation in floodplainFloodplainLand expected to flood at a stated frequency, where building carries extra conditions.
The proposed lowest floor elevation of any proposed building based upon National Geodetic Vertical Datum of 1929.
- Manufactured homeManufactured homeA dwelling built in a factory to a federal standard and transported to the site. flood elevation
Manufactured homes that are placed or substantially improved on sites shall be elevated on a permanent foundation such that the lowest floor of the manufactured home is elevated to or above the base flood elevation.
Other
- Sidewalk width5 ft
Construction of a 5' sidewalk along the street and roadway and a 5' sidewalk leading to the structure.
- Site plan scale50 ft per inch
The scale shall not be less than fifty (50) feet to one (1) inch.
- Site plan sheet size
All site plans shall be submitted on twenty-four-inch by thirty-six-inch sheets.
- Site plan validity5 years
Approval of a site plan submitted under the provisions of this article shall expire five (5) years after the date of such approval unless building permits have been obtained for construction in accordance therewith.
From the ordinance
Every site plan shall be prepared in accordance with the following specifications: ... Construction of a 5' sidewalk along the street and roadway and a 5' sidewalk leading to the structure.