Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Approval criteria
The use is compatible with the character and appearance of the surrounding neighborhood; does not create a demand on public water or sanitary sewer services exceeding design capacity; does not generate traffic exceeding street capacity; does not increase flood potential; conforms with setback, yard, frontage, lot area, parking, signage, screening requirements; furthers comprehensive plan.
- Construction commencement deadline12 months
Construction shall begin or the use of land for which a conditional use permit has been obtained shall commence within 12 months from the effective date of such permit; otherwise, such permit shall become void.
- Discontinuance voids permit2 years
In the event that the use allowed by a conditional use permit is discontinued for a period of two consecutive years, the conditional use permit shall become void.
- Planning commission report deadline60 days
Within 60 calendar days from the date that any application for a conditional use permit is referred to it... the planning commission shall submit its report and recommendation to the town council.
- Revocation final after30 days
A decision to revoke a conditional use permit shall become final 30 calendar days after the date the decision is rendered, unless appealed.
From the ordinance
An application for a conditional use permit shall be in writing... Construction shall begin or the use of land for which a conditional use permit has been obtained shall commence within 12 months from the effective date of such permit; otherwise, such permit shall become void.