Chesterfield County Unincorporated, Virginia · General provision
19.2-52
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Board of Supervisors decision deadline12 months
The Board of Supervisors shall render a decision upon the proposal within 12 months after the date of the Board's first public hearing on the proposal.
- Planning Commission recommendation deadline100 days
The Planning Commission shall report a recommendation to the Board of Supervisors within 100 days from the date of the first public hearing on the proposal.
- Waiting period after denial12 months
An application for a conditional use shall not be accepted for review within 12 months after the date of denial of the same, or a substantially similar, request.
From the ordinance
The Planning Commission shall report a recommendation to the Board of Supervisors within 100 days from the date of the first public hearing on the proposal.