Dimensional standards
Servicing
- Geographic extent
- Applies to all battery energy storage systems.
Extracted standards
5 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Decommissioning agreement required
Prior to approval, applicant shall enter into written decommissioning agreement.
- Layered fire protection required
Sufficient layered fire protection approach as determined by Chesapeake Fire Department.
- Maximum lighting at lot line0.5 footcandles
Direct or reflected illumination does not exceed one-half (0.5) footcandles above background measured at the lot line.
- Minimum setbackSetbackThe distance a building must be held back from a lot line. from property lines300 ft
Any battery energy storage system shall be setback three hundred (300) feet from all property lines.
- Reduced setbackSetbackThe distance a building must be held back from a lot line. with risk analysis100 ft
City council may reduce distance to no less than 100 feet if independent risk analysis provided.
From the ordinance
Any battery energy storage system shall be setback three hundred (300) feet from all property lines.