Ashland, Virginia · General provision

Sec 21-281

Dimensional standards

Extracted standards

7 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Maximum antenna enclosure volume6 cuft

    Each antenna is located inside an enclosure of no more than six (6) cubic feet in volume

  • Maximum associated equipment volume28 cuft

    All other wireless equipment associated with the facility has a cumulative volume of no more than twenty-eight (28) cubic feet

  • Micro-wireless facility maximum antenna length11 in

    exterior antenna, if any, no more than eleven (11) inches in length

  • twelve (12) inches in height

  • Micro-wireless facility maximum length24 in

    micro-wireless facility is a small cell facility that is no greater than twenty-four (24) inches in length

  • Micro-wireless facility maximum width15 in

    fifteen (15) inches in width

  • Removal time after consent withdrawal120 days

    must be removed by the wireless services provider or wireless infrastructure provider that installed the facility or is otherwise responsible for the facility within 120 days after the owner of the existing structure withdraws or revokes its consent

From the ordinance

The installation of a small cell facility by a wireless services provider or wireless infrastructure provider on an existing structure may be permitted on any lot in any zoning district subject to approval by the Zoning Administrator of a small cell facility zoning permit and compliance with the provisions below.
Sec 21-281