Albemarle County Unincorporated, Virginia · General provision

Sec. 5.8

Extracted standards

2 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Maximum duration for temporary industrialized building3 years

    No temporary industrialized building shall remain on the site for more than three years after obtaining the zoning clearance

  • Maximum extension for temporary industrialized building2 years

    the Zoning Administrator may extend the duration of the zoning clearance beyond three years for up to two successive periods of one year each

From the ordinance

No temporary industrialized building shall remain on the site for more than three years after obtaining the zoning clearance; provided that the Zoning Administrator may extend the duration of the zoning clearance beyond three years for up to two successive periods of one year each
Sec. 5.8