Albemarle County Unincorporated, Virginia · General provision
Sec. 5.1.18
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Temporary construction headquarters duration
The headquarters shall be authorized on the site for a period beginning no earlier than 30 days prior to the commencement of actual construction and ending no later than 30 days after completion of the last building
- Minimum distance from temporary construction yardYardThe open space left between a building and its lot line — the space a setback creates. to preexisting dwelling150 ft
and (ii) closer than 150 feet to any preexisting dwelling not owned or leased by the owner
- Minimum distance from temporary construction yardYardThe open space left between a building and its lot line — the space a setback creates. to public street right-of-way50 ft
no portion of a yard shall be located: (i) closer than 50 feet to any public street right-of-way
From the ordinance
The headquarters shall be authorized on the site for a period beginning no earlier than 30 days prior to the commencement of actual construction and ending no later than 30 days after completion of the last building to be constructed in the project or 30 days after active construction on the site is suspended or abandoned, whichever occurs first (hereinafter, the "ending date"). ... The yard shall be located within the same site where the construction project is located. In addition, no portion of a yard shall be located: (i) closer than 50 feet to any public street right-of-way existing prior to the recording of the subdivision plat served by the yard or existing prior to the commencement of the construction project; and (ii) closer than 150 feet to any preexisting dwelling not owned or leased by the owner of the subdivision or construction project served by the yard.