Other

  • Maximum duration12 months

    period not to exceed 12 months

  • Necessity requirement

    necessary to serve a valid purpose, including but not limited to a construction office, a sales office, or a temporary classroom

  • Removal requirement

    removed upon the expiration of the temporary permit

  • Temporary permit required

    subject to the issuance of a temporary permit by the zoning administrator

From the ordinance

A temporary industrialized building may be permitted in any zoning district for a period not to exceed 12 months, subject to the issuance of a temporary permit by the zoning administrator, and shall comply with the following requirements: a. The temporary industrialized building shall be necessary to serve a valid purpose, including but not limited to a construction office, a sales office, or a temporary classroom. b. The temporary industrialized building shall comply with the requirements of the Virginia Uniform Statewide Building Code. c. The temporary industrialized building shall be removed upon the expiration of the temporary permit. d. The zoning administrator may extend the temporary permit for additional periods not to exceed 12 months each, upon a finding that the temporary industrialized building is still necessary to serve a valid purpose.