Albemarle County Unincorporated, Virginia · General provision
Sec. 5.1.26
Dimensional standards
Lot
Extracted standards
3 individual requirements pulled out of this section’s prose, each with the sentence it came from.
Other
- Minimum lot areaMinimum lot areaThe smallest parcel on which the district allows anything to be built.435,600 sqftsq ftSquare feet. An acre is 43,560 sq ft; a typical suburban lot is 7,000–10,000.
located on a lot of not less than 10 acres
- Minimum setbackSetbackThe distance a building must be held back from a lot line. from lot line100 ft
located not less than 100 feet from any lot line
permitted only as authorized by special use permit under section 33.5
From the ordinance
Hydroelectric power generation shall be permitted only as authorized by special use permit under section 33.5, and shall comply with the following requirements: a. The hydroelectric power generation facility shall comply with the requirements of the Federal Energy Regulatory Commission and the Virginia Department of Environmental Quality. b. The hydroelectric power generation facility shall be located on a lot of not less than 10 acres. c. The hydroelectric power generation facility shall be located not less than 100 feet from any lot line.