Abingdon, Virginia · General provision

Section 7-2-44

Extracted standards

4 individual requirements pulled out of this section’s prose, each with the sentence it came from.

Other

  • Small cell facilities shall be permitted by right in all zoning districts subject to the following general performance standards.

  • Maximum antenna volume6 cubic ft

    Each antenna is located inside an enclosure of, or the antenna and all its exposed elements could fit within an imaginary enclosure of, no more than six cubic feet.

  • Maximum equipment volume28 cubic ft

    Excluding electric meter, concealment, telecommunication demarcation boxes, backup power systems, grounding equipment, power transfer switches, cutoff switches, and vertical cable runs for the connection of power and other services, all other equipment associated with the facility does not exceed 28 cubic feet, or such higher limit as may be established by the Federal Communications Commission.

  • Review time60 days

    Permit applications for the installation of small cell facilities shall be approved or disapproved within 60 days of receipt of the complete application.

From the ordinance

In accordance with Code of Virginia, § 15.2-2316.4, small cell facilities shall be permitted by right in all zoning districts subject to the following general performance standards.
Section 7-2-44